Restoration Log
| Week 0 |
28 February 2007: Extraction Day |
| Week 1 |
07 March 2007: Disassembly begins (front suspension, cooling system, engine) |
| Week 3 |
22 March 2007: Disassembly continues (rear suspesnsion, interior) |
| Week 6 |
11 April 2007: Disassembly continues (electrics, interior, engine) |
| Week 8 |
27 April 2007: Disassembly complete, chassis ready for body shop |
| Week 14 |
06 June 2007: Bodywork assessment, new/rebuilt parts coming/going |
| Week 21 |
25 July 2007: Engine work, body stripped, more parts coming/going |
| Week 25 |
25 August 2007: Body damage |
| Week 31 |
01 October 2007: Engine parts and redone brake calipers |
| Week 40 |
09 December 2007: Engine pre-assembly and rebuilt suspension parts |
| Week 50 |
22 February 2008: More engine pre-assembly, rear brakes, repro wheels |
| Week 57 |
10 April 2008: SV tail lights saga |
| Week ?? |
13 February 2009: Sump modifications and airbox tops |
| Week ?? |
6 July 2009: Bodywork progress |
| Year 3 |
12 April 2010: Engine assembly, Webers, ancillaries, bodywork |
| Year 3 |
2 August 2010: Engine complete, front of chassis nearly complete |
Click here to return to the Lamborghini Miura page.